APA PRF CONTRACT - Successful Completion May 2016
03 Jun 2016
After award of the Parmelia Relocation Forrestfield (PRF) Project by APA Group in December 2015, P&A Welding Pty Ltd has now successfully completed the relocation of a 1.5km section of the DN350 Parmelia Gas Pipeline to facilitate the new Forrestfield Airport Link. Consisting of construction of the new pipeline, two bypass pipelines, live line welding of hot tap fittings, tie-in to existing Parmelia Gas Pipeline and removal of the redundant pipeline, this project was completed on schedule and within budget. We appreciate the efforts made by all P&A Welding personnel , the APA Representatives on site and all subcontractors in completing this project safely and LTI free.
Photos
of the activities on site can be seen in the Gallery under “Projects” at
the header of this page.