APA Group - Murrin Murrin Delivery Station - Skid Pipe and Supports Fabrication and Installation
20 Sep 2017
P&A Welding Pty Ltd successfully completed the above project in
March 2017, during a very tight shutdown window of 5 days (20-24/3/17)
for APA Group, which was awarded in February 2017. Skid Pipe
fabrication, testing and surface treatment were completed in our Bibra
Lake Workshop. Initial Civil Works were required on site and these
commenced and were completed early March 2017. P&A Welding Pty Ltd
were restricted to a 5-day shutdown window for installation of the
pipework, skids and support steelwork.